State research record

Kansas pole attachment rules, in writing.

Who regulates the pole you are attaching to in Kansas, what rate standard applies, where a dispute actually goes and whether cooperative and municipal poles are covered. This is the record we work from, published so you can read it yourself.

Last verified October 28, 2026 · not certified under Section 224(c) · 11 authorities cited
The record

Kansas

KansasKS

Not certified under Section 224(c)Last verified October 28, 2026
Cooperative poles
Conditionally, and the condition is a member vote. Cooperatives are public utilities by default under K.S.A. 66-104(a), with Commission jurisdiction over electric public utilities under K.S.A. 66-101, and a cooperative becomes exempt only by a deregulation election of its own members under K.S.A. 66-104d. That section preserves Commission authority over a short list of named subjects after an exemption, and pole attachments are not among them. Cooperatives sit outside the federal pole attachment statute in all events under 47 U.S.C. 224(a)(1). Which Kansas cooperatives have voted out is not established, so it is a question to ask of each cooperative. A cooperative that takes a federal BEAD subgrant can pick up federal pole attachment obligations across its whole pole footprint, but no Kansas cooperative has been established as the pole owner of record under an executed subgrant agreement.
Municipal poles
No. K.S.A. 66-104(b) and (c) place a municipally owned utility inside the corporate limits, and within three miles of them, outside the Kansas act and under the city's own control, and municipal poles sit outside the federal pole attachment statute under 47 U.S.C. 224(a)(1). Contract and ordinance only. The one Kansas provision on a charge for attaching to a governmental authority's own facilities, K.S.A. 66-2019(d)(1), belongs to a wireless siting statute whose definitions exclude any telephone or electrical utility pole at K.S.A. 66-2019(b)(21), so it gives a wireline attacher nothing and is not a rate constraint on municipal poles.
Rate standard
No Kansas rate methodology for pole attachments exists, and Kansas has set no ceiling, no presumptive rate and no adopted federal benchmark. Investor-owned electric and telephone poles run to the federal formulas, because Kansas has never certified. A cooperative that has not deregulated is held only to the general standard that a public utility's charges not be unreasonable, unfair, unjust, unjustly discriminatory or unduly preferential, under K.S.A. 66-101 with K.A.R. 82-1-220(a), and that standard has never been applied to a pole attachment charge in any located Kansas decision. A cooperative that has deregulated, and a municipal system, are contract only. No Kansas investor-owned pole attachment tariff was located.
Where a dispute goes
Kansas Corporation Commission for a cooperative that has not deregulated, by formal complaint under K.A.R. 82-1-220(a), which is open to any person and not only to a customer. No Commission order applying that rule to a pole attachment charge has been located in two research runs, so the route is available on the text and unproven in practice. A corporation cannot enter an appearance at the Commission except by its attorney, under K.A.R. 82-1-228(d)(2), and that attorney must be admitted in the Kansas courts of record or admitted elsewhere with Kansas local counsel already appearing. District court on the contract for a cooperative that has deregulated and for municipal poles. Investor-owned disputes go to the FCC. No Kansas filing deadline or limitation period is established for any owner class.
Confidence
High confidence on non-certification, on the cooperative default jurisdiction and the member vote exemption mechanism, on the municipal exclusions, on the complaint grounds and on the corporate appearance rule. Every Kansas text behind those was re-read first hand on 2026-10-28 and is unamended, except non-certification, which is carried at the programme reading of DA 22-630 and was not re-read. Provisional on the negative findings proved by absence, and on whether the Commission will apply the complaint rule to a pole attachment charge brought by a non customer attacher, which is untested. Good confidence on the state's published BEAD subrecipient list and Provisional on whether the cooperative named there is the pole owner of record. Which cooperatives have deregulated is not established.

AuthoritiesK.S.A. 66-101K.S.A. 66-104(a)K.S.A. 66-104(b)K.S.A. 66-104(c)K.S.A. 66-104dK.S.A. 66-2019(b)(21)K.S.A. 66-2019(d)(1)K.A.R. 82-1-220(a)K.A.R. 82-1-228(d)(2)47 U.S.C. 224(a)(1)FCC Public Notice DA 22-630

Read the chip above as one fact and no more: whether Kansas has certified under Section 224(c) that it regulates pole attachments itself. It does not settle your pole. Cooperative and municipal poles sit outside federal jurisdiction whether or not a state has certified, so the two owner class lines are the ones that answer the question for the invoice in front of you.

This record is worked from the statute and the order that made it rather than from a summary of one. The confidence line is tied to its source: where a conclusion rests on weaker ground the record says so, because a hedge you can see is what makes the confident answers worth believing. The method is set out in how PoleProof researches and verifies, and how a cleared rule enters an audit is on the methodology page.

Back to the state research ledger · 50 jurisdictions on file

Scope

How to use this, and how to check it.

Every conclusion above names the authority it rests on, so you can go read that authority and decide whether you agree. That is the point of publishing the record rather than asserting the result.

This is general information about the rules. On a specific dispute, your own counsel is the person to ask. PoleProof performs financial and cost review of what you have been billed rather than engineering evaluation of what the pole owner determined was necessary. Rules change, so check the authorities named above against their current text.